SM5 delivered a refurbishment for Peter Marsh Consulting and The Henley College - fitting out 3 floors of learning space for the college’s T Level students.

Client Requirements:

SM5 have successfully delivered a refurbishment for Peter Marsh Consulting and The Henley College - fitting out 3 floors of learning space for the college’s T Level students. Whilst keeping the college semi-operational, SM5 Developments carried out an extensive strip out and fit out during the 2023 summer shut down. The project was awarded to SM5 Developments as a design & build contract with SM5 responsible for further developing the design brief developed by PMC.

Works Include:
  • Extensive strip out and demolition works
  • Upgrade of services including new A/C, ventilation and power
  • The preparation and decoration of all walls new and old
  • New ceilings - MF and laying grid to all areas 
  • Reconfiguring of classrooms and installation of glazing to create lighter learning spaces
  • Installation of new flooring
  • New wall and floor finishes
  • Forming new structural openings
  • Feature finishes in all areas
  • Fire stopping works
  • Install of new door-set and steel car ramp to allow for vocational engineering classroom 

 